Electric train ES104 “Finishist”
Available with 2023 year. Built 51 composition.
EVS360 – Yeelectric train Inhigh speed group Sinara, 360 km/h - design speed. Available with 2026 year for Ural locomotives. Under construction 1 composition.
High-speed electric train for the St. Petersburg – Moscow line. Planned, that the train will operate at speeds up to 360 km/h. The compositions will be formed from 8 cars with the ability to work according to CME up to 16 carriages. One of the carriages will be designed for a bistro, and the rest are divided into 4 class: comfort, standard, first and business.
At the factory "Ural locomotives" welding of the first ones is completed 2 carriages. These cars are planned to be transferred for testing to 2027 year. In 2028 year, the train should enter the new line of the Moscow-St. Petersburg high-speed railway. The construction of the highway is proceeding in parallel with the creation of rolling stock.
"Beliy krechet" – this is the first Russian train, originally designed for design speed 400 km/h. With its help, it is planned to reduce travel time from Moscow to St. Petersburg to 2 hours 15 minutes. The commercial speed of the Moscow – St. Petersburg line is planned to be 360 km/h, which exceeds the speed of trains EVS1 / EVS2 "Sapsan" (250 km/h, structural ICE 3 – 350 km/h) and most European high speed lines (300-320 km/h).
The cost of one composition is estimated at approximately 5,34 billion rubles. K 2028 expected to be delivered 28 trains per 149 billion rubles, in 2029 year - still 8, in 2030 - 7. Total required 66 compositions, 3 of which will be in reserve. According to government contract, to the end 2030 years must be transferred to the customer 41 eight-car train. The service life of the train is designed for 30 years.

Available with 2023 year. Built 51 composition.

Issued in 2012-2014 years. Built 54 composition.

Issued in 2010-2023 years. Built 181 electric locomotive.

Issued in 1952-1959 years. Built 75 electric locomotives.